NBCC tells Supreme Court it will exit Supertech projects if homebuyers oppose involvement
State-owned NBCC has told the Supreme Court it will withdraw from completing 16 stalled Supertech housing projects if homebuyers do not want its involvement. The court reserved its order after some homebuyers claimed NBCC had made no progress, while two companies offered to invest funds for completi
State-owned NBCC on Monday told the Supreme Court that it would exit the stalled Supertech housing projects if homebuyers do not want its involvement. The matter came up before a bench comprising Chief Justice Surya Kant and Justices Joymalya Bagchi and V Mohana, which reserved its order.
“I (NBCC) do not want to be an unwanted child in the entire proceedings,” Attorney General R Venkataramani, appearing for NBCC, told the bench. “The eight per cent rate of the project cost is a government-fixed rate and if nobody wants NBCC, then we would like to exit.”
The submission followed claims by counsel for some homebuyers that NBCC had done nothing on these projects. Venkataramani said NBCC is a public sector undertaking, not a developer. The court observed its concern was for the homebuyers and who would execute the projects. The counsel for homebuyers urged the bench to appoint a court receiver, noting most homebuyers have paid up to 90 per cent of the property cost but received nothing.
The top court was informed that two companies have given proposals and are willing to invest funds for completing the stalled projects. “They will invest funds but who will execute these projects?” the bench asked, noting NBCC is not the agency that executes projects itself. The bench made clear it did not want any additional burden on homebuyers.
The Supreme Court had earlier upheld a 12 Dec 2024 order of the National Company Law Appellate Tribunal (NCLAT) asking NBCC to complete 16 of Supertech’s 30 housing projects, comprising 49,748 homes in Uttar Pradesh, Uttarakhand, Haryana and Karnataka. Around 27,000 homebuyers are awaiting delivery of these houses. The NCLAT had directed NBCC to start the award of work before 31 Mar 2025 and begin construction from 1 May 2025.
NBCC had proposed to complete the 16 projects in three phases. Phase 1 covers Eco-Village-2 (Greater Noida), Romano (Noida), Capetown (Noida), Czar Suites (Greater Noida), Eco-Village-3 (Greater Noida), Sports Village (Greater Noida) and Eco-citi (Noida). Phase 2 includes Northeye (Noida), Upcountry (Yamuna Expressway), Eco-Village-1 (Greater Noida), Meerut Sports City (Meerut) and Green Village (Meerut). Phase 3 covers Hilltown (Gurugram), Aravile (Gurugram), Rivercrest (Rudrapur), Doon Square (Dehradun) and Micasa (Bengaluru).
Union Bank of India initiated insolvency proceedings against Supertech under the Insolvency and Bankruptcy Code on 20 Mar 2021, claiming more than Rs 431 crore as of 31 Jan 2021, plus accrued interest.