CoA flags PUP over P489 million in unused funds and delayed student stipends

The Commission on Audit flagged the Polytechnic University of the Philippines for leaving P489.35 million in budget allocations unutilized in 2025. Infrastructure projects worth P412.88 million were delayed, while student financial assistance totalling P45.17 million faced delays of up to 359 days.

CoA flags PUP over P489 million in unused funds and delayed student stipends

The Polytechnic University of the Philippines (PUP) left hundreds of millions of pesos in budget allocations unutilized in 2025, while infrastructure projects were delayed and student financial assistance remained unreleased, according to the Commission on Audit (CoA). In its 2025 audit report, CoA said PUP obligated P3.28 billion, or 87.02 per cent of its P3.77-billion total allotments, leaving P489.35 million unobligated. Of this amount, P38.45 million was reverted to the Bureau of the Treasury.

The university also failed to utilize P573.26 million, or 34.90 per cent, of its P1.64-billion Special Trust Fund (STF) budget during the year. CoA attributed the low-budget utilization partly to planning and execution weaknesses, noting that PUP recorded zero disbursements for capital outlay and had P136.64 million in unreleased appropriations due to its failure to submit required budgetary supporting documents.

Infrastructure development was also affected by implementation delays. Six PUP infrastructure projects worth P412.88 million, covering calendar years 2023 and 2024, were delayed or deficiently implemented due to inadequate planning, weak monitoring, and poor coordination with the Department of Public Works and Highways. These shortcomings deprived beneficiaries of timely access to improved educational facilities and exposed the projects to budget lapses, fund reversions and possible cost increases, CoA said.

The audit also found delays in the distribution of student financial assistance. Stipends under the Tulong-Dunong Program amounting to P45.17 million were delayed by as much as 359 days, with P8.10 million remaining unreleased as of the end of 2025. Meanwhile, Tertiary Education Subsidy grants worth P13.46 million experienced delays ranging from six to 889 days. Another P4.05 million remained unreleased as of Dec. 31, 2025.

CoA also flagged PUP’s implementation of the Free Higher Education program, saying its guidelines under Republic Act No. 10931, or the Universal Access to Quality Tertiary Education Act, were not fully operationalized. State auditors cited the university’s failure to prioritize poor but academically capable students and the lack of an adequate mechanism for financially capable students to voluntarily opt out of the program and pay their tuition and other fees.

As of Dec. 31, 2025, the university had P259.50 million in remaining audit disallowances, although it had no unsettled audit suspensions. PUP management agreed to implement CoA’s recommendations, including strengthening internal controls, improving project monitoring, and ensuring the timely release of student financial assistance. Despite these findings, CoA rendered an unmodified opinion on PUP’s 2025 financial statements.